Treatment Capacity
(m3/day) |
Tentative Year of
Commissioning |
|
|
Increased by |
Total |
|
Existing STKSTW |
- |
1,660 |
- |
Temporary Sewage Treatment Plant |
- |
2,500 |
2019 |
Phase 1 Expansion* |
3,340 |
5,000 |
2021 |
Phase 2 Expansion |
5,000 |
10,000 |
End 2030 |
Note:* Proposed submarine outfall will also
commission together with the phase 1 expanded STKSTW.
Tentatively,
the construction of the Project will last for 49 months and is scheduled to
commence in 3rd quarter of 2017.
Table 1.1 Designated Project Status of the Project Components
Project Component |
DP/ |
Remarks |
Increase the treatment capacity of STKSTW to5,000 m3/day at ADWF by 2021 (Phase 1 Expansion); |
DP |
Sewage treatment works with an installed capacity of more than 5,000 m3/day and a boundary of which is less than 200 m from the nearest boundary of an existing residential area under Schedule 2 Part I Item F.2 of the EIAO |
Increase the treatment capacity of STKSTW to 10,000 m3/day at ADWF by 2030 (Phase 2 Expansion); |
DP |
Sewage treatment works with an installed capacity of more than 5,000 m3/day and a boundary of which is less than 200 m from the nearest boundary of an existing residential area under Schedule 2 Part I Item F.2 of the EIAO |
Marine construction works for the diffuser |
Non-DP |
The works is more than 500m form the nearest boundary of an existing or planned area under Schedule 2 Part I Item C.2(a) of the EIA and it is more than 100m from a seawater intake point |
Construct a TSTP |
Non-DP |
Sewage treatment works with an installed capacity not more than 5,000 m3/day |
Demolish the STKSPS and decommission the rising mains between STKSPS and STKSTW |
Non-DP |
The works would not fall partly or wholly within any of the sensitive areas as stated in Schedule 2 Part 1 Item Q.1 of the EIAO |
Construct new gravity sewer |
Non-DP |
The works would not fall partly or wholly within any of the sensitive areas as stated in Schedule 2 Part 1 Item Q.1 of the EIAO |
Construct a new submarine outfall |
DP |
Schedule 2 Part I Item F.6 of the EIAO |
An activity for the reuse of treated sewage effluent from a treatment plant |
DP |
Schedule 2 Part I Item F.4 of the EIAO |